Investigation and remediation of contaminated sites

REDEVELOPMENT AND PROJECT DEVELOPMENT "BUSINESSPARK ELBUFER"

Project details

The city of Wedel is developing the Elbufer BusinessPark on the site of the former mineral oil plant in Wedel. Due to the historical use of the site, the soil and groundwater were contaminated with pollutants. Remediation has been and is being carried out:

  • Remediation of soil and groundwater contamination
  • Master plan procedure with subsequent urban land use planning
  • Construction of transport infrastructure and supply and disposal facilities
  • Laying a district heating pipeline
  • Relocation and operation of a groundwater purification plant
  • Preparation of harbour area for subsequent use

Client: City of Wedel
Overall project duration: ongoing since 2006
Total project costs: > € 25 million
Area size: approx. 18.6 ha

BIG's share of benefits:

  • Services in accordance with the project management service profile as per AHO: Project stages 1 - 5 and action areas A - E
  • Project management for the entire project (incl. cost and contract management, participation in approval procedures, technical advice to the client)
  • Preparation and updating of the time schedule incl. control of the capacity framework, control of specialist planners and execution services
  • Participation in the preparation of the award and contract structure, preparation of the award documents and participation in the award of engineering and execution services
  • Review of supplementary audits, cost controlling, participation in acceptances
  • Preparation of a remediation plan in accordance with § 13 BBodSchG, taking into account the more extensive requirements under planning law (healthy living and working conditions).
  • Site management of the remediation and deconstruction work incl. waste disposal management
  • Safety coordination according to § 3 BaustellV in accordance with RAB 30 and TRGS 524 / DGUV-R 101-004

SIMILAR PROJECTS

error: Content is protected !!!